Background on Claudia Sheinbaum and Her Role
Claudia Sheinbaum Pardo is the current Head of Government of Mexico City, serving as the city’s equivalent to a mayor. Previously, she was Mexico’s Secretary of Environment from 2012 to 2018. Her role in the recent power outage in the Yucatán Peninsula highlights her importance as a key figure in addressing critical infrastructure issues affecting multiple states.
Power Outage Details and Impact
On the afternoon of [insert date], a power outage affected approximately 2.262 million users across the states of Campeche, Yucatán, and Quintana Roo in the Yucatán Peninsula. The outage was triggered by maintenance work on 400 kV lines (ESA A3Q20/A3Q30 LT), causing a failure that led to the shutdown of 9 power plants with 16 units in the Southeast region.
Causes and Immediate Response
The power outage occurred at 14:19 (Central Time) due to maintenance activities on transmission lines. As a result, nine power plants in the Southeast region went offline, affecting a significant portion of the population. In response, the Comisión Federal de Electricidad (CFE) and Centro Nacional de Control de Energía (CENACE) immediately initiated efforts to restore electrical service.
Progress and Restoration
By 20:30 (Central Time), substantial progress had been made in restoring power across the Southeast. The majority of affected users regained full electrical service, thanks to the coordinated efforts of CFE and CENACE.
Claudia Sheinbaum’s Statement and Next Steps
Through her official social media channels, Claudia Sheinbaum expressed gratitude for the public’s understanding and patience during this challenging situation. She also emphasized her anticipation of the official reports from both the Comisión Federal de Electricidad (CFE) and CENACE to determine the root cause of this power failure.
Key Questions and Answers
- Who was affected by the power outage? Approximately 2.262 million users across Campeche, Yucatán, and Quintana Roo states in the Yucatán Peninsula were impacted.
- What caused the power outage? The outage was triggered by maintenance work on 400 kV transmission lines, which led to the shutdown of nine power plants in the Southeast region.
- Who is responsible for restoring power? The Comisión Federal de Electricidad (CFE) and Centro Nacional de Control de Energía (CENACE) are working together to restore electrical service.
- When was full power restored? By 20:30 (Central Time), substantial progress had been made in restoring power across the Southeast, with most users regaining full electrical service.
- What is Claudia Sheinbaum’s role in this situation? As the Head of Government of Mexico City and former Secretary of Environment, Claudia Sheinbaum is responsible for coordinating responses to critical infrastructure issues affecting multiple states.